400 A Overhead Service & Sub-Panel Upgrade – 8-Unit Apartment, Van Nuys, CA

GET A FREE QUOTE

5/5

4.9 RATING

5/5

4.9 RATING

5/5

4.9 RATING

 

400-Amp Overhead Service & Sub-Panel Replacement – 8-Unit Apartment • Van Nuys, CA

Project Snapshot

Property Type: 8-unit apartment building + house meter
Existing Condition: Federal Pacific 200 A main & nine recalled FPE sub-panels
Driver: Insurance carrier required full replacement of FPE equipment
Scope: Replace main service, meters, and 9 sub-panels • Manage all LADWP / LADBS approvals
New Equipment: 9-gang 400 A Square D overhead service • (9) 8/16-circuit Square D sub-panels
Authority Coordination: LADWP Service Planning & Crew • LADBS Inspection


1. Background & Challenge

The owner risked losing insurance coverage unless every Federal Pacific component—the main switch and nine sub-panels—was eliminated.
Space constraints and tenant occupancy made same-day energization a must.

  • Limit power-off window to within daytime hours.
  • Secure LADWP meter-spot and shutdown scheduling.
  • Fit a 400 A, 9-gang stack in a tight exterior alcove.

2. Solution Overview

Branover Contractors engineered and installed a 400 A Square D overhead service—one meter per apartment plus a house meter—along with nine 8/16-circuit Square D sub-panels.

Key design steps:

  1. Load Calculation & Single-Line Diagram – NEC 220 demand calc; plans to LADWP.
  2. Utility Coordination – Meter-spot approval.
  3. Permit & Inspection – Electrical permit with LADBS; rough & final passed.
  4. Installation Highlights – 3″ riser, new weatherhead, 500 MCM copper conductors; upgraded grounding.

Phase Key Activities

  1. Site Assessment & Engineering — Load calc • Single-line • Material take-off
  2. Utility & Permit Approvals — Submit to LADWP • Pull LADBS permit
  3. Pre-Construction Coordination — Book shutdown • Notify tenants
  4. Demolition & Temporary Power — Remove FPE gear • Provide temp feeds
  5. Main Service Installation — Set 400 A 9-gang Square D stack • Ground/bond
  6. Sub-Panel Replacements — Swap 9 units sequentially • Label circuits
  7. Inspection & Re-Energization — Pass LADBS • LADWP sets meters

4. Results & Benefits

  • Safety & Compliance — All recalled gear removed; NEC-2023 compliant.
  • Future Capacity — 400 A service ready for EV chargers or HVAC upgrades.
  • Insurance Savings — Renewal secured; surcharge avoided.
  • Tenant Experience — Outages pre-scheduled and communicated; zero complaints.



5. Final Installation

Square D 400 amp electrical service

Newly installed 400 A Square D meter center & service riser (Van Nuys, CA)

6. Key Takeaways

  1. One-Stop Service — We streamline utility and city approvals.
  2. First-Time Inspection Passes — Thorough pre-inspection checklists.
  3. Minimal Downtime — Phased swaps keep tenants powered and happy.
  4. Future-Ready Designs — Sized for tomorrow’s loads, not yesterday’s.

Scroll to Top