400-Amp Overhead Service Upgrade & Sub-Panel Replacement – 8-Unit Apartment Building · Los Angeles, CA

GET A FREE QUOTE

5/5

4.9 RATING

5/5

4.9 RATING

5/5

4.9 RATING

400-Amp Overhead Service Upgrade & Sub-Panel Replacement – 8-Unit Apartment Building • Los Angeles, CA

Project Snapshot

Property Type 8-unit, two-story apartment building
Existing Condition Federal Pacific 200 A main & aging FPE sub-panels
Scope Replace entire service and nine sub-panels
New Equipment 9-gang 400 A Square D overhead service, (9) 12/24-circuit Square D sub-panels
Authority Coordination LADWP Service Planning & Field Crew • LADBS Inspection

Old Federal Pacific meter bank
Before – Old Federal Pacific meter bank
New 400 A 9-gang meter bank
After – New 400 A 9-gang meter bank
Painted-over FPE sub-panel
Before – Painted-over FPE sub-panel
New Square D sub-panel
After – New Siemens sub-panel

1. Background & Challenge

The owner’s insurer flagged the building’s original Federal Pacific equipment as a fire hazard and threatened non-renewal unless it was replaced. In addition to safety concerns, the 200 A service left no capacity for future EV chargers or HVAC upgrades. The owner needed a fast, code-compliant solution that minimized tenant downtime.

2. Solution Overview

Branover Contractors engineered and installed a 400 A, 9-gang Square D overhead service—one meter per apartment plus a dedicated house meter—along with nine 12/24-circuit sub-panels mounted inside each unit.

Key design steps:

  1. Load Calculation & Single-Line Diagram
    • Single-line & load calculation for confirmed 400 A capacity requirement.
    • Single-line diagram and load calculation submitted to LADWP Service Planning.
  2. Utility Coordination
    • Obtained meter spot approval within five business days.
    • Scheduled with LADWP Field Crew to set new meters.
  3. Permit & Inspection
    • Pulled electrical permit with LADBS.
    • Passed electrical service and final inspections.
  4. Installation Highlights
    • 3″ galvanized riser, new weatherhead, and 500 MCM copper conductors.
    • Bonded & grounded.
    • Sub-panels labeled and circuits re-terminated.

Phase Key Activities

1. Site Assessment & Engineering — Perform load calculations • Draft single-line diagram • Scope materials

2. Utility & Permit Approvals — Submit plans to LADWP for meter spot • Pull LADBS electrical permit

3. Pre-Construction Coordination — Schedule shutdown window with LADWP Field Crew • Notify tenants of brief, staggered outages

4. Demolition & Temporary Power — De-energize and remove Federal Pacific gear • Provide temporary feeds for essential circuits

5. Main Service Installation — Install 400 A 9-gang Square D meter stack, riser, weatherhead, conductors • Complete grounding & bonding

6. Sub-Panel Replacements — Swap nine 12/24-circuit sub-panels one unit at a time • Re-terminate and label branch circuits

7. Inspection & Re-Energization — Pass LADBS inspection • LADWP installs new meters and restores permanent power

4. Results & Benefits

  • Safety & Compliance – Eliminated high-failure FPE gear; installation passed LADBS.
  • Capacity for Growth – 400 A service future-proofs the building for solar, EV charging, or heat-pump retrofits.
  • Insurance Savings – Owner secured renewal and avoided a 30 % premium surcharge.
  • Property Value – Modern service infrastructure is a selling point for prospective buyers and tenants.
  • Tenant Experience – Planned outages communicated in advance; no reported appliance damage or lost rent days.

5. Key Takeaways

  1. One-Stop Service – From design to final meter set, we streamline utility and city approvals.
  2. First-Time Inspection Passes – Thorough pre-inspection checklists mean no costly re-visits.
  3. Minimal Downtime – Phased sub-panel swaps keep tenants powered and happy.
  4. Future-Ready Designs – We size services for tomorrow’s loads, not yesterday’s

Scroll to Top